Substation / point of interconnection ยท Karnes County
Tap on PAWNEESW5 (#5725) - COLETO7A (#8164) Line
1 active project totalling 203 MW is queued to connect at Tap on PAWNEESW5 (#5725) - COLETO7A (#8164) Line in Karnes County, Texas, according to ERCOT's October 2026 report.
Active capacity
203 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0072 | Charro Creek Solar 3 SLF | Solar | 203 | FIS Requested | 12/31/2029 | 0 |