26INR0072 · Solar · Karnes County
Charro Creek Solar 3 SLF
Charro Creek Solar 3 SLF is a 203 MW solar project in Karnes County, Texas, connecting at Tap on PAWNEESW5 (#5725) - COLETO7A (#8164) Line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0072
- Capacity
- 203 MW
- Fuel
- Solar (PV)
- County
- Karnes County
- Interconnecting entity
- Charro Creek Solar LLC
- Projected COD
- 12/31/2029
- Entered queue
- 02/15/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/15/2023Entered the queue with 203 MW, projected COD 12/31/2029
- 02/15/2023Screening → FIS Requested
Other projects at this substation