Substation / point of interconnection ยท Jim Hogg County
Tap 345 kV 80355 DelSol7A - 80079 Cruce CKT 2
1 active project totalling 302 MW is queued to connect at Tap 345 kV 80355 DelSol7A - 80079 Cruce CKT 2 in Jim Hogg County, Texas, according to ERCOT's October 2026 report.
Active capacity
302 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0242 | Ciervo Wind | Wind | 302 | FIS Requested | 12/31/2028 | 0 |