ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Jackson County

Tap 69kV #5522 Edna - #5518 El Toro SW

2 active projects totalling 245 MW are queued to connect at Tap 69kV #5522 Edna - #5518 El Toro SW in Jackson County, Texas, according to ERCOT's October 2026 report.

Active capacity
245 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0251Sayle Solar SLFSolar122FIS Requested05/31/20280
27INR0260Sayle Storage SLFBESS122FIS Requested05/31/20280