Substation / point of interconnection ยท Jackson County
Tap 69kV #5522 Edna - #5518 El Toro SW
2 active projects totalling 245 MW are queued to connect at Tap 69kV #5522 Edna - #5518 El Toro SW in Jackson County, Texas, according to ERCOT's October 2026 report.
Active capacity
245 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0251 | Sayle Solar SLF | Solar | 122 | FIS Requested | 05/31/2028 | 0 |
| 27INR0260 | Sayle Storage SLF | BESS | 122 | FIS Requested | 05/31/2028 | 0 |