27INR0260 · BESS · Jackson County
Sayle Storage SLF
Sayle Storage SLF is a 122 MW battery storage project in Jackson County, Texas, connecting at Tap 69kV #5522 Edna - #5518 El Toro SW. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0260
- Capacity
- 122 MW
- Fuel
- BESS (BA)
- Substation
- Tap 69kV #5522 Edna - #5518 El Toro SW
- County
- Jackson County
- Interconnecting entity
- Sayle Storage LLC
- Projected COD
- 05/31/2028
- Entered queue
- 05/22/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/22/2024Entered the queue with 122 MW, projected COD 05/31/2028
- 05/22/2024Screening → FIS Requested
Other projects at this substation
| Sayle Solar SLF | Solar | 122 MW | FIS Requested |