LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Guadalupe County

7044 Marion 345kV

2 active projects totalling 660 MW are queued to connect at 7044 Marion 345kV in Guadalupe County, Texas, according to ERCOT's October 2026 report.

Active capacity
660 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0145Calpine Guadalupe PeakersGas450FIS Requested05/30/20300
27INR0093Guadalupe Battery Storage ProjectBESS210FIS Requested05/30/20300