27INR0093 · BESS · Guadalupe County
Guadalupe Battery Storage Project
Guadalupe Battery Storage Project is a 210 MW battery storage project in Guadalupe County, Texas, connecting at 7044 Marion 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/30/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0093
- Capacity
- 210 MW
- Fuel
- BESS (BA)
- Substation
- 7044 Marion 345kV
- County
- Guadalupe County
- Interconnecting entity
- Guadalupe Power Partners, LP
- Projected COD
- 05/30/2030
- Entered queue
- 11/14/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/22/2024Screening → FIS Requested
- 11/14/2023Entered the queue with 210 MW, projected COD 05/30/2030
Other projects at this substation