2 active projects totalling 615 MW are queued to connect at Tap 345kV 1729 Valley South – Anna Switch 2373 in Grayson County, Texas, according to ERCOT's October 2026 report.
Active capacity
615 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0605 | White Bright BESS | BESS | 314 | FIS Requested | 04/16/2029 | 0 |
| 26INR0300 | Whitewright Solar 2 | Solar | 302 | FIS Requested | 05/02/2028 | 0 |