26INR0300 · Solar · Grayson County
Whitewright Solar 2
Whitewright Solar 2 is a 302 MW solar project in Grayson County, Texas, connecting at Tap 345kV 1729 Valley South – Anna Switch 2373. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/02/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0300
- Capacity
- 302 MW
- Fuel
- Solar (PV)
- County
- Grayson County
- Interconnecting entity
- SunWR, LLC
- Projected COD
- 05/02/2028
- Entered queue
- 11/07/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/07/2023Entered the queue with 302 MW, projected COD 05/02/2028
- 11/07/2023Screening → FIS Requested
Other projects at this substation
| White Bright BESS | BESS | 314 MW | FIS Requested |