Substation / point of interconnection ยท Goliad County
Tap 138kV 8590 Tuleta - 8595 Euler
1 active project totalling 256 MW is queued to connect at Tap 138kV 8590 Tuleta - 8595 Euler in Goliad County, Texas, according to ERCOT's October 2026 report.
Active capacity
256 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 21INR0223 | Tulsita Solar | Solar | 256 | Sync Approved | 09/15/2026 | 0 |