Substation / point of interconnection ยท Goliad County

Tap 138kV 8590 Tuleta - 8595 Euler

1 active project totalling 256 MW is queued to connect at Tap 138kV 8590 Tuleta - 8595 Euler in Goliad County, Texas, according to ERCOT's October 2026 report.

Active capacity
256 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
21INR0223Tulsita SolarSolar256Sync Approved09/15/20260