21INR0223 · Solar · Goliad County
Tulsita Solar
Tulsita Solar is a 256 MW solar project in Goliad County, Texas, connecting at Tap 138kV 8590 Tuleta - 8595 Euler. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/15/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0223
- Capacity
- 256 MW
- Fuel
- Solar (PV)
- Substation
- Tap 138kV 8590 Tuleta - 8595 Euler
- County
- Goliad County
- Interconnecting entity
- Ray Ranch Solar LLC
- Projected COD
- 09/15/2026
- Entered queue
- 12/05/2018
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/30/2024Energization Approved → Sync Approved
- 10/22/2024IA Signed → Energization Approved
- 03/01/2024FIS Requested → FIS Approved
- 09/19/2022FIS Approved → IA Signed
- 05/17/2019Screening → FIS Requested
- 12/05/2018Entered the queue with 256 MW, projected COD 09/15/2026