Substation / point of interconnection ยท Franklin County
Tap 345 kV 11699 Woodard Switch - 1695 Monticello SES
2 active projects totalling 246 MW are queued to connect at Tap 345 kV 11699 Woodard Switch - 1695 Monticello SES in Franklin County, Texas, according to ERCOT's October 2026 report.
Active capacity
246 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0150 | Lupinus Solar 1 | Solar | 162 | IA Signed | 09/13/2027 | 0 |
| 24INR0153 | Lupinus Storage 1 | BESS | 84 | FIS Approved | 09/13/2027 | 0 |