Substation / point of interconnection ยท Franklin County
Hagansport Switch (old Monticello Tap bus# 1794)
2 active projects totalling 367 MW are queued to connect at Hagansport Switch (old Monticello Tap bus# 1794) in Franklin County, Texas, according to ERCOT's October 2026 report.
Active capacity
367 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0154 | Lupinus Solar 2 | Solar | 242 | IA Signed | 04/03/2027 | 0 |
| 24INR0155 | Lupinus Storage 2 | BESS | 124 | IA Signed | 04/03/2027 | 0 |