Substation / point of interconnection ยท Fayette County
138kV WARDA #7312.
1 active project totalling 202 MW is queued to connect at 138kV WARDA #7312. in Fayette County, Texas, according to ERCOT's October 2026 report.
Active capacity
202 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0189 | Staccato BESS | BESS | 202 | IA Signed | 05/28/2027 | 0 |