Counties / Texas
Fayette County power projects
Fayette County, Texas has 4 active power projects totalling 1,016 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 816 MW (80%). The largest single project is Lightcycle Energy Storage (410 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
4
1.0 GW capacity
IA signed or later
2
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Fayette County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Lightcycle Energy Storage | BESS | 410 | 9073 HOLMAN 345 kV | FIS Requested | 03/01/2030 |
| South Tripoint BESS | BESS | 204 | 7286 L_FAYETT8_1Y 138kV | Screening | 05/30/2030 |
| Staccato BESS | BESS | 202 | 138kV WARDA #7312. | IA Signed | 05/28/2027 |
| Monument Hill Solar | Solar | 200 | Tap 345kV 7055 Fayette - 9074 Lytton Springs | IA Signed | 06/30/2029 |
For residents and landowners
- What power projects are planned in Fayette County?
- ERCOT's October 2026 report lists 4 active projects in Fayette County totalling 1,016 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.