Substation / point of interconnection ยท Coke County
76090 Divide Switchyard 345kV
1 active project totalling 220 MW is queued to connect at 76090 Divide Switchyard 345kV in Coke County, Texas, according to ERCOT's October 2026 report.
Active capacity
220 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0155 | Coke BESS | BESS | 220 | FIS Requested | 04/10/2028 | 0 |