Substation / point of interconnection ยท Calhoun County
Dokmai 138kV Substation (bus #80090)
2 active projects totalling 554 MW are queued to connect at Dokmai 138kV Substation (bus #80090) in Calhoun County, Texas, according to ERCOT's October 2026 report.
Active capacity
554 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0019 | HyFuels Green Lake Solar | Solar | 347 | FIS Requested | 12/01/2027 | 0 |
| 27INR0466 | Wolfram Storage | BESS | 207 | FIS Requested | 12/01/2027 | 0 |