Calhoun County power projects
Calhoun County, Texas has 4 active power projects totalling 850 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 542 MW (64%). The largest single project is HyFuels Green Lake Solar (347 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
4
0.8 GW capacity
IA signed or later
1
25% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Calhoun County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| HyFuels Green Lake Solar | Solar | 347 | Dokmai 138kV Substation (bus #80090) | FIS Requested | 12/01/2027 |
| Wolfram Storage | BESS | 207 | Dokmai 138kV Substation (bus #80090) | FIS Requested | 12/01/2027 |
| Tres Bahias Solar | Solar | 195 | 8140 Joslin 138kV | Sync Approved | 08/31/2026 |
| Vaca Storage | BESS | 101 | 138kV 8723 Cangrejo | FIS Requested | 07/01/2029 |
For residents and landowners
- What power projects are planned in Calhoun County?
- ERCOT's October 2026 report lists 4 active projects in Calhoun County totalling 850 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.