LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Calhoun County power projects

Calhoun County, Texas has 4 active power projects totalling 850 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 542 MW (64%). The largest single project is HyFuels Green Lake Solar (347 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
4
0.8 GW capacity
IA signed or later
1
25% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Calhoun County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
HyFuels Green Lake SolarSolar347Dokmai 138kV Substation (bus #80090)FIS Requested12/01/2027
Wolfram StorageBESS207Dokmai 138kV Substation (bus #80090)FIS Requested12/01/2027
Tres Bahias SolarSolar1958140 Joslin 138kVSync Approved08/31/2026
Vaca StorageBESS101138kV 8723 CangrejoFIS Requested07/01/2029

For residents and landowners

What power projects are planned in Calhoun County?
ERCOT's October 2026 report lists 4 active projects in Calhoun County totalling 850 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.