Substation / point of interconnection ยท Bell County
Tap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2
2 active projects totalling 201 MW are queued to connect at Tap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2 in Bell County, Texas, according to ERCOT's October 2026 report.
Active capacity
201 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0344 | Hermes Solar | Solar | 100 | Sync Approved | 06/12/2026 | 0 |
| 24INR0365 | Hermes Storage | BESS | 100 | Sync Approved | 08/18/2026 | 0 |