ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0344 · Solar · Bell County

Hermes Solar

Hermes Solar is a 100 MW solar project in Bell County, Texas, connecting at Tap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 06/12/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0344
Capacity
100 MW
Fuel
Solar (PV)
Interconnecting entity
Bell 1 Solar, LLC
Projected COD
06/12/2026
Entered queue
09/21/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/17/2026
    Energization Approved → Sync Approved
  • 02/23/2026
    IA Signed → Energization Approved
  • 04/19/2024
    FIS Requested → FIS Approved
  • 11/08/2023
    FIS Approved → IA Signed
  • 06/01/2022
    Screening → FIS Requested
  • 09/21/2021
    Entered the queue with 100 MW, projected COD 06/12/2026

Other projects at this substation

Hermes StorageBESS100 MWSync Approved