LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Atascosa County

Tap 138kV ROSSVILLESB8 (5718) to OAKSSW8 (5713)

2 active projects totalling 101 MW are queued to connect at Tap 138kV ROSSVILLESB8 (5718) to OAKSSW8 (5713) in Atascosa County, Texas, according to ERCOT's October 2026 report.

Active capacity
101 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0208Strawberry Dunes Solar SLFSolar101FIS Requested06/30/20280
28INR0209Strawberry Dunes BESS SLFBESS0FIS Requested06/30/20280