LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
31INR0018 · Solar · Pecos County

Permian I Solar

Permian I Solar is a 1,126 MW solar project in Pecos County, Texas, connecting at Tap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
31INR0018
Capacity
1,126 MW
Fuel
Solar (PV)
Interconnecting entity
S&S Renewables, LLC
Projected COD
06/30/2030
Entered queue
12/29/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/29/2025
    Entered the queue with 1,126 MW, projected COD 06/30/2030
  • 12/29/2025
    Screening → FIS Requested

Other projects at this substation

Permian I WindWind636 MWFIS Requested
Permian I Natural GasGas1,247 MWFIS Requested