LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
30INR0089 · BESS · Runnels County

Mistflower Energy Center Storage

Mistflower Energy Center Storage is a 313 MW battery storage project in Runnels County, Texas, connecting at Tap 345kV 60072 Odysseus – 60040 Bluff Creek. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0089
Capacity
313 MW
Fuel
BESS (BA)
Interconnecting entity
Mistflower Energy Center LLC
Projected COD
06/01/2030
Entered queue
02/25/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/12/2026
    Screening → FIS Requested
  • 02/25/2026
    Entered the queue with 313 MW, projected COD 06/01/2030

Other projects at this substation

No other projects at this substation.