ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
30INR0088 · Solar · Runnels County

Mistflower Energy Center Solar

Mistflower Energy Center Solar is a 402 MW solar project in Runnels County, Texas, connecting at Tap 345kV 60072 ODYSSEUS7A– 60040 BLF_CRK7A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0088
Capacity
402 MW
Fuel
Solar (PV)
Interconnecting entity
Mistflower Energy Center LLC
Projected COD
06/01/2030
Entered queue
02/19/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/19/2026
    Entered the queue with 402 MW, projected COD 06/01/2030
  • 02/19/2026
    Screening → FIS Requested