30INR0085 · Wind · Pecos County

Gravitas I Wind

Gravitas I Wind is a 636 MW wind project in Pecos County, Texas, connecting at Tap 345kV Solstice (60404) - Bakersfield (76002) Double circuit line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0085
Capacity
636 MW
Fuel
Wind (WT)
Interconnecting entity
S&S Renewables, LLC
Projected COD
06/30/2030
Entered queue
03/18/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/18/2026
    Entered the queue with 636 MW, projected COD 06/30/2030
  • 03/18/2026
    Screening → FIS Requested

Other projects at this substation

Gravitas I SolarSolar1,125 MWFIS Requested
Gravitas I Natural GasGas1,247 MWFIS Requested