30INR0076 · Solar · Runnels County
Zuma Solar
Zuma Solar is a 201 MW solar project in Runnels County, Texas, connecting at Tap 345kV 11263 Fisk Switch - 11406 Central Bluff Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/09/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 30INR0076
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Runnels County
- Interconnecting entity
- Zuma Solar, LLC
- Projected COD
- 09/09/2030
- Entered queue
- 03/26/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/26/2026Entered the queue with 201 MW, projected COD 09/09/2030
- 03/26/2026Screening → FIS Requested