LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
30INR0076 · Solar · Runnels County

Zuma Solar

Zuma Solar is a 201 MW solar project in Runnels County, Texas, connecting at Tap 345kV 11263 Fisk Switch - 11406 Central Bluff Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/09/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0076
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Zuma Solar, LLC
Projected COD
09/09/2030
Entered queue
03/26/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/26/2026
    Entered the queue with 201 MW, projected COD 09/09/2030
  • 03/26/2026
    Screening → FIS Requested