30INR0053 · Solar · Pecos County

MRR Solar

MRR Solar is a 500 MW solar project in Pecos County, Texas, connecting at Solstice Substation #60384 -AEP. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0053
Capacity
500 MW
Fuel
Solar (PV)
Interconnecting entity
Antler Peak Solar, LLC
Projected COD
07/01/2030
Entered queue
07/18/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/15/2026
    FIS Requested → IA Signed
  • 07/18/2025
    Entered the queue with 500 MW, projected COD 07/01/2030
  • 07/18/2025
    Screening → FIS Requested