29INR0354 · Gas · Reeves County
Wolf Bone North Energy Center
Wolf Bone North Energy Center is a 1,174 MW natural gas project in Reeves County, Texas, connecting at TNMP Cowpen 345kV Substation POIB 38044 (4 mile transmission line will connect POI at customer substation to POIB in the Cowpen substation). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/28/2031.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0354
- Capacity
- 1,174 MW
- Fuel
- Gas (CC)
- County
- Reeves County
- Interconnecting entity
- NRG Wolf Bone Energy Center LLC
- Projected COD
- 02/28/2031
- Entered queue
- 09/01/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Entered the queue with 1,174 MW, projected COD 02/28/2031
- 09/01/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.