LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0320 · BESS · Wilson County

Nockenut Springs Storage 3

Nockenut Springs Storage 3 is a 209 MW battery storage project in Wilson County, Texas, connecting at Tap the 345 kV Elm Creek (#5133) - Shaula (#5380) Line, CPS. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/05/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0320
Capacity
209 MW
Fuel
BESS (BA)
Interconnecting entity
Pecan Springs Energy, LLC
Projected COD
06/05/2029
Entered queue
04/01/2026
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/01/2026
    Entered the queue with 209 MW, projected COD 06/05/2029
  • 04/01/2026
    Screening → FIS Requested

Other projects at this substation

Nockenut Springs Storage 1BESS209 MWFIS Requested
Nockenut Springs Storage 2BESS209 MWFIS Requested