LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0183 · Solar · Pecos County

Pecos Flats Solar III

Pecos Flats Solar III is a 302 MW solar project in Pecos County, Texas, connecting at Tap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/05/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0183
Capacity
302 MW
Fuel
Solar (PV)
Interconnecting entity
Glass Mountain Solar, LLC
Projected COD
02/05/2029
Entered queue
09/05/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/05/2025
    Entered the queue with 302 MW, projected COD 02/05/2029
  • 09/05/2025
    Screening → FIS Requested

Other projects at this substation

Pecos Flats Solar IISolar302 MWFIS Requested