29INR0162 · Gas · Reeves County

Wolf Bone North Energy Center (OLD)

Withdrawn

Wolf Bone North Energy Center (OLD) is a 1,204 MW natural gas project in Reeves County, Texas, connecting at Tap 345 kV 60404 SOLTICE7A - 18669 TOYAHCRK_5 Ckt 1. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0162
Capacity
1,204 MW
Fuel
Gas (CC)
Interconnecting entity
NRG Wolf Bone Energy Center LLC
Projected COD
11/01/2029
Entered queue
09/19/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/04/2026
    Listed as cancelled
  • 09/19/2025
    Entered the queue with 1,204 MW, projected COD 11/01/2029
  • 09/19/2025
    Screening → FIS Requested