29INR0147 · Solar · Pecos County
Selenite Springs Solar
Selenite Springs Solar is a 253 MW solar project in Pecos County, Texas, connecting at Tap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Switching Station. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0147
- Capacity
- 253 MW
- Fuel
- Solar (PV)
- County
- Pecos County
- Interconnecting entity
- Selenite Springs Solar, LLC
- Projected COD
- 08/30/2028
- Entered queue
- 04/18/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/24/2025FIS Requested → IA Signed
- 04/18/2025Entered the queue with 253 MW, projected COD 08/30/2028
- 04/18/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.