29INR0050 · Solar · Atascosa County
Amphion Solar Phase 1
Amphion Solar Phase 1 is a 181 MW solar project in Atascosa County, Texas, connecting at TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt FOWRTN_SMIGL2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0050
- Capacity
- 181 MW
- Fuel
- Solar (PV)
- County
- Atascosa County
- Interconnecting entity
- Amphion Solar, LLC
- Projected COD
- 09/01/2028
- Entered queue
- 10/10/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/10/2024Entered the queue with 181 MW, projected COD 09/01/2028
- 10/10/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.