28INR0434 · Wind · Jim Hogg County
Viento Bravo Wind
Viento Bravo Wind is a 366 MW wind project in Jim Hogg County, Texas, connecting at Tap 345kV 80220 Cenizo - 80079 Cruce Ckt-1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/06/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0434
- Capacity
- 366 MW
- Fuel
- Wind (WT)
- County
- Jim Hogg County
- Interconnecting entity
- Webb Wind, LLC
- Projected COD
- 07/06/2028
- Entered queue
- 09/23/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/31/2025FIS Requested → IA Signed
- 09/23/2025Entered the queue with 366 MW, projected COD 07/06/2028
- 09/23/2025Screening → FIS Requested
Other projects at this substation
| Mirando Valley Wind | Wind | 479 MW | IA Signed |