28INR0375 · Wind · Jim Hogg County
Barranca Wind 1
Barranca Wind 1 is a 301 MW wind project in Jim Hogg County, Texas, connecting at Tap the 345 kV CENIZO (#80225) - DELSOL (#80307) line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0375
- Capacity
- 301 MW
- Fuel
- Wind (WT)
- County
- Jim Hogg County
- Interconnecting entity
- Barranca Wind Energy, LLC
- Projected COD
- 06/01/2028
- Entered queue
- 07/09/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/09/2025Entered the queue with 301 MW, projected COD 06/01/2028
- 07/09/2025Screening → FIS Requested