28INR0270 · BESS · Brown County
Soluce Bravo Storage
Soluce Bravo Storage is a 303 MW battery storage project in Brown County, Texas, connecting at tap 345kV 1444 BROWN - 11441 CORN TRAIL SW CKT2. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 09/17/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0270
- Capacity
- 303 MW
- Fuel
- BESS (BA)
- County
- Brown County
- Interconnecting entity
- BNPB1, LLC
- Projected COD
- 09/17/2029
- Entered queue
- 01/13/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/13/2025Entered the queue with 303 MW, projected COD 09/17/2029
Other projects at this substation
| Soluce Bravo Solar | Solar | 81 MW | Screening |