28INR0269 · Solar · Brown County
Soluce Bravo Solar
Soluce Bravo Solar is a 81 MW solar project in Brown County, Texas, connecting at tap 345kV 1444 BROWN - 11441 CORN TRAIL SW CKT2. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 09/17/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0269
- Capacity
- 81 MW
- Fuel
- Solar (PV)
- County
- Brown County
- Interconnecting entity
- BNPB1, LLC
- Projected COD
- 09/17/2029
- Entered queue
- 01/13/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/13/2025Entered the queue with 81 MW, projected COD 09/17/2029
Other projects at this substation
| Soluce Bravo Storage | BESS | 303 MW | Screening |