LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0212 · Solar · Upton County

Badger Solar

Badger Solar is a 280 MW solar project in Upton County, Texas, connecting at Tap 345kV 59903 Bearkat - 76000 L_NORTMC5_1Y. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/25/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0212
Capacity
280 MW
Fuel
Solar (PV)
Interconnecting entity
174 Power Global Properties, LLC
Projected COD
05/25/2029
Entered queue
11/27/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Capacity 302 → 280 MW
  • 11/27/2024
    Entered the queue with 302 MW, projected COD 05/25/2029
  • 11/27/2024
    Screening → FIS Requested

Other projects at this substation

Badger BESSBESS139 MWFIS Requested