28INR0207 · BESS · Knox County
Wagon Timber Storage
Wagon Timber Storage is a 54 MW battery storage project in Knox County, Texas, connecting at 6110 Munday East 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/03/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0207
- Capacity
- 54 MW
- Fuel
- BESS (BA)
- Substation
- 6110 Munday East 138kV
- County
- Knox County
- Interconnecting entity
- Wagon Timber Storage, LLC
- Projected COD
- 09/03/2029
- Entered queue
- 12/05/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/05/2024Entered the queue with 54 MW, projected COD 09/03/2029
- 12/05/2024Screening → FIS Requested
Other projects at this substation
| Wagon Timber Solar | Solar | 172 MW | FIS Requested |