Knox County power projects

Knox County, Texas has 8 active power projects totalling 1,861 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,228 MW (66%). The largest single project is Oriole Solar (504 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
8
1.9 GW capacity
IA signed or later
4
50% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Knox County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Oriole SolarSolar504Tap 345kV 6076 Foxtail - 60791 PerigeeIA Signed12/29/2028
Zeissel SolarSolar452#60094 Joule 345kVIA Signed06/30/2028
West Munday WindWind352Tap 345kV 60703 Gauss7D – 60712 QuasarIA Signed08/31/2029
Wagon Timber SolarSolar1726110 Munday East 138kVFIS Requested09/03/2029
Oriole BESBESS150Tap 345kV 6076 Foxtail - 60791 PerigeeIA Signed12/29/2028
Lemma SolarSolar1016088 Benjamin AEP 138kVFIS Requested07/01/2028
Knox County Moore StorageBESS776110 Munday East Substation 138kVFIS Requested06/30/2028
Wagon Timber StorageBESS546110 Munday East 138kVFIS Requested09/03/2029
Sundance SolarSolar301Not listedWithdrawnn/a
Zeissel Storage SLFBESS0Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Knox County?
ERCOT's October 2026 report lists 8 active projects in Knox County totalling 1,861 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.