28INR0116 · BESS · Tarrant County

Salazar BESS

Salazar BESS is a 128 MW battery storage project in Tarrant County, Texas, connecting at 2068 Rosen Heights 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/11/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0116
Capacity
128 MW
Fuel
BESS (BA)
Interconnecting entity
Salazar Energy Storage LLC
Projected COD
07/11/2028
Entered queue
08/27/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/27/2024
    Entered the queue with 128 MW, projected COD 07/11/2028
  • 08/27/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.