Tarrant County power projects
Tarrant County, Texas has 4 active power projects totalling 792 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 792 MW (100%). The largest single project is Team Ranch Storage (307 MW battery storage). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
4
0.8 GW capacity
IA signed or later
1
25% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Tarrant County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Team Ranch Storage | BESS | 307 | 1869 Benbrook Switch 345kV | FIS Requested | 03/01/2027 |
| Anglin BESS | BESS | 206 | 1883 EVRSW 138kV | FIS Requested | 09/30/2028 |
| Stockyard Grid Batt | BESS | 151 | 2082 Hicks 138kV | IA Signed | 12/14/2028 |
| Salazar BESS | BESS | 128 | 2068 Rosen Heights 138kV | FIS Requested | 07/11/2028 |
For residents and landowners
- What power projects are planned in Tarrant County?
- ERCOT's October 2026 report lists 4 active projects in Tarrant County totalling 792 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.