LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0606 · Gas · Williamson County

Big Watt Mustang Power

COD delayed 1×

Big Watt Mustang Power is a 449 MW natural gas project in Williamson County, Texas, connecting at Tapping the 138 kV line from Taylor (Bus#3658) to Thorndale North (Bus#3659). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/15/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0606
Capacity
449 MW
Fuel
Gas (CC)
Interconnecting entity
Big Watt Power Mustang LLC
Projected COD
12/15/2028
Entered queue
03/02/2026
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/01/2027 → 12/15/2028 (+15 months)
  • 03/02/2026
    Entered the queue with 449 MW, projected COD 09/01/2027
  • 03/02/2026
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.