Moccasin Storage
Moccasin Storage is a 603 MW battery storage project in Jones County, Texas, connecting at Tap 345kV #60707 Kirchhoff - #60515 Clear Crossing CKT-1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0452
- Capacity
- 603 MW
- Fuel
- BESS (BA)
- County
- Jones County
- Interconnecting entity
- ENGIE IR Holdings LLC
- Projected COD
- 07/01/2028
- Entered queue
- 01/15/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/15/2025Entered the queue with 603 MW, projected COD 07/01/2028
- 01/15/2025Screening → FIS Requested