27INR0382 · BESS · Victoria County
Calico BESS
Calico BESS is a 205 MW battery storage project in Victoria County, Texas, connecting at Tap 138 kV 8723 CANGREJO4A - 8721 BEECHER4A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0382
- Capacity
- 205 MW
- Fuel
- BESS (BA)
- County
- Victoria County
- Interconnecting entity
- Nova Clean Energy LLC
- Projected COD
- 06/01/2028
- Entered queue
- 03/14/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/14/2025Entered the queue with 205 MW, projected COD 06/01/2028
- 03/14/2025Screening → FIS Requested
Other projects at this substation