27INR0257 · BESS · Goliad County
Double A Storage SLF
Double A Storage SLF is a 0 MW battery storage project in Goliad County, Texas, connecting at Tap 69kV 5678 Schroeder - 5675 Big Oak. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0257
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- Tap 69kV 5678 Schroeder - 5675 Big Oak
- County
- Goliad County
- Interconnecting entity
- Double A Storage, LLC
- Projected COD
- 05/31/2028
- Entered queue
- 05/30/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/30/2024Entered the queue with 0 MW, projected COD 05/31/2028
- 05/30/2024Screening → FIS Requested
Other projects at this substation
| Double A Solar SLF | Solar | 133 MW | FIS Requested |