ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0248 · Solar · Goliad County

Double A Solar SLF

Double A Solar SLF is a 133 MW solar project in Goliad County, Texas, connecting at Tap 69kV 5678 Schroeder - 5675 Big Oak. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0248
Capacity
133 MW
Fuel
Solar (PV)
Interconnecting entity
Double A Solar, LLC
Projected COD
05/31/2028
Entered queue
05/30/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/30/2024
    Entered the queue with 133 MW, projected COD 05/31/2028
  • 05/30/2024
    Screening → FIS Requested

Other projects at this substation

Double A Storage SLFBESS0 MWFIS Requested