27INR0224 · BESS · Victoria County

Leopard BESS

Leopard BESS is a 264 MW battery storage project in Victoria County, Texas, connecting at 8721 Beecher 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/28/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0224
Capacity
264 MW
Fuel
BESS (BA)
Interconnecting entity
Bobcat Energy Center, LLC
Projected COD
02/28/2029
Entered queue
04/05/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/09/2025
    FIS Requested → IA Signed
  • 04/05/2024
    Entered the queue with 264 MW, projected COD 02/28/2029
  • 04/05/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.