27INR0206 · BESS · Medina County
Chacon Creek
Chacon Creek is a 189 MW battery storage project in Medina County, Texas, connecting at (#8962) LYTLE4A 138KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0206
- Capacity
- 189 MW
- Fuel
- BESS (BA)
- Substation
- (#8962) LYTLE4A 138KV
- County
- Medina County
- Interconnecting entity
- Cattlemen BESS LLC
- Projected COD
- 10/31/2027
- Entered queue
- 03/14/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/14/2024Entered the queue with 189 MW, projected COD 10/31/2027
- 03/14/2024Screening → FIS Requested