27INR0146 · Solar · Pecos County

Larrea Solar

COD delayed 1×

Larrea Solar is a 232 MW solar project in Pecos County, Texas, connecting at Tap 345kV 76002 Bakerfield - 60404 Solstice CKT#1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/18/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0146
Capacity
232 MW
Fuel
Solar (PV)
Interconnecting entity
Greasewood IV LLC
Projected COD
09/18/2029
Entered queue
01/03/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/18/2027 → 09/18/2029 (+24 months)
  • 06/05/2024
    Screening → FIS Requested
  • 01/03/2024
    Entered the queue with 232 MW, projected COD 09/18/2027

Other projects at this substation

No other projects at this substation.